Personnel, equipment and materials required for plastic runway construction

(i) Personnel

1. Construction Team Director: Project Manager 1

2. Site Leader: 1 Site Supervisor

3, full-time quality staff: 1

4. Part-time and part-time construction workers and security staff: 2 people

5, construction team personnel: 15-20 people

塑胶跑道施工

(b) Machines

1, high-speed mixer 1-2

2. Four-wheel carts 6-8

3, 1 sweeper or high power blower 1

4, paving machine 1

5, spraying machine 1

6, drawing machine 1

7, a group of other construction manual appliances

(c) Materials

1, the required materials:

Base oil PJT-190

Adhesive PJT-194

Plastic spray material PJT-195

Color paste, line paint, etc.

Black rubber particles 1-3mm

Red EPDM particle 0.5-1.5mm

2, material ratio:

(1) Primary treatment material: PJT-190;

(2) Substrate: Use a professional mixer to mix the slurry with the adhesive and black rubber particles in a ratio of 1:4;

(3) Compact layer: fill it with PJT-190+ filler;

(4) Surface spray coating: The surface material (PJT194: PJT195=2:1 is mixed) is mixed with EPDM powder and EPDM particles in a mixing ratio of 1:5:0.25.

3, material packaging, stacking and precautions:

(1) Bulk liquid materials are stacked on both sides of the runway in the parallel direction of the local prevailing wind direction of the construction season. The PJT-194 is packed in 200kg vats and is stacked vertically in a single layer. The pJT-190 and PJT-195 are used for piling. All are stacked in 30kg or 15kg keg, and the stacking height cannot be higher than 2 stories.

(2) The solvent used for dilution is generally packed in 170kg vats or packed in 15kg kegs, concentrated in a dedicated area and sent to special persons for management.

(3) Solid materials such as EPDM rubber particles and black rubber particles are piled on both sides of the runway in the parallel direction of the local prevailing wind direction at the time of the construction. The stacking force shall be firm and not loosened, and be covered with a waterproof stripe to avoid moisture.

(4) The construction tools are stacked on the side of the runway, and the power supply side adopts the special distribution box for construction and the “three-phase five-wire system” for safe connection.

(5) Machines are specially operated by qualified personnel. Special attention should be paid to personnel safety during operation.

(6) The ratio of materials is strictly controlled by the company's professionals and it is poundable at any time.

(7) The material should be stirred for more than 1 minute per barrel and thoroughly mixed.

Related Reading:

"Plastic Runway Construction Requirements and Maintenance"

Http://

If you have any requirements, please feel free to contact with us, look forward to hear from you.

Material: PVC & PU optional;

With extra big pump, facial hole & pillow and pure sponge inside;

Headrest removable, backrest and legrest adjustable, and legrest can be rotated 90 degree, the footrest can be extended;

The two armrest can be adjusted up and down, and can rotated in 360degree;

This part can put arms when the whole bed in flat position;

this metal bar can put arms & hands when tattoo the back, it`s stainless steel material;

footrest

capacity is 200kgs

Standard export package

 

We can custom any styles any size of Electric Facial Bed, Hydraulic Facial Bed, wood Facial Bed , Massage Table , facial bed, facial massage chair, Shampoo Chair, Barber Chair , styling chair, child chair, Waiting Chair, dressing mirror, reception table, pedicure spa, Nail Table , massage chair, master chair,tattoo stool,tattoo salon chair, tattoo artist chair,tattoo furniture,trolley, Bed Cover , footstep and cushion according to your requirements.

 

Tattoo Chair

Tattoo Chair,Black Tattoo Chair,Adjustable Tattoo Chair,Hydraulic Tattoo Chairs

ChaoHui Beauty Salon Equipment Co., Ltd. , https://www.chaohuibeauty.com